Sample | Mep Work Progress Report

Current MEP works are 46% complete; mechanical and electrical rough-ins progressing on Floors 1–6, plumbing risers 90% complete to rooftop, and HVAC ductwork on Levels 2–4 behind schedule by 5 days due to material delay.

Green Tower Commercial Complex – Phase 1 Report No: MEP-024 Reporting Period: Oct 16 – Oct 22, 2024 Date of Issue: Oct 23, 2024 Weather Conditions: Partly Cloudy / 22°C (Suitable for MEP works) Prepared By: John Carter (MEP Manager) mep work progress report sample

[Number] Requests for Inspection (RFI) submitted; [Number] approved, [Number] pending minor corrections. 6. Planned Activities for Next Week Current MEP works are 46% complete; mechanical and